Valencia issue Nou Mestalla update
2nd June 2026
Construction of the Nou Mestalla continues to make steady progress, with the project now entering the final stages of preparation before the lifting of the main roof structure, which will cover the 70,044 seats of Valencia CF’s future home.
In recent days, the installation of all auxiliary scaffolding required for the tension ring cable system has been completed.
Significant progress has also been made on the protective structures within the stands ahead of the deployment of the radial cables, several of which have already been installed. At the same time, work has continued on the stadium façade, stair towers and a number of interior areas.